Data Center Capacity
We track data center projects from announcement to completion. Every megawatt on record is traced to its source.
Our View
Announced Capacity Is Not Supply
There is a shortage of data center power. Most of the numbers describing it are announcements not facts.
Ask us where 20 MW can be energized inside 18 months. The answer comes from analysis, not press releases.


The Market
Supply is the bottleneck
Vacancy in the primary North American markets is almost zero, and most capacity under construction is leased before it is energized. It is important to know which announced projects energize, and when.
1.4%1
Vacancy across the primary North American markets
80.4%1
Of all capacity under construction is already preleased
7,481MW1
Under construction in the primary markets mid-2026
1 CBRE, North America Data Center Trends, H1 2026.
Deliverable Research
Find Real Megawatts
Track important project details, sourced from permits, dockets, and utility filings.
01
Facility, campus, and operator
Asset name and the company that controls it.
02
Operational and planned MW
Planned and actual megawatts for the project today.
03
Available MW by delivery date
Leasable supply versus announced supply.
04
Utility and interconnection status
Shows whether the power will arrive, and when.
05
Rack density and liquid cooling
Settles whether the hall can carry GPU loads.
06
Electricity price and contract terms
Prices the power where the terms are disclosed.
07
Contiguous available capacity
Matches large single-tenant requirements to real space.
08
Owner and authorized contact
Locates the authorized contact and how to reach them.
09
Source, confidence, last verified
Makes every figure auditable to its source and date.

Project record
S7‑VA‑0142
Loudoun County, Virginia
Hyperscale campus · developer-owned · three buildings
Last verified
2026‑10‑30
96 MW approvedApproved interconnection · 96 MW
144 MW announced · no interconnection on file
Sample
- 1 · Energized · 32 MW
- 2 · Under construction · 64 MW
- 3 · Announced · 144 MW
| Date | Filing | Stage | MW | ||
|---|---|---|---|---|---|
| 2025‑02‑11 | Developer release: three-building campus | Announcement | 240 | ||
| 2025‑08‑04 | County site plan approval | Permission | — | ||
| 2026‑03‑19 | County building permit, Bldg 2 | Construction | 64 | ||
| 2026‑06‑02 | Utility: service energized, Bldg 1 | Energization | 32 | ||
| 2026‑09‑30 | Utility: interconnection agreement, Bldgs 1–2 | Capacity | 96 | ||
| Deliverable on record · confidence high | Deliverable capacity on record · confidence high | 96 | |||
Not the 240 MW in the announcement. The utility has agreed to serve buildings 1 and 2; building 3 has no interconnection on file.
Project Details
From First Filing to First Megawatt
Every project advances through four stages as the filings arrive. Announced and delivered megawatts are tracked separately.
Research Process
Discover. Verify. Deliver
01
Discover
We find and research planning permits, utility dockets, interconnection filings, environmental approvals, property records, and company announcements.
02
Verify
Each project is staged on the filings, not the announcement. Every figure is traced to its source, rated for confidence, and re-verified on a schedule.
03
Deliver
Subscribers receive database exports, real-time project alerts, and custom research scoped to markets or requirements.
Built For
One Project. Every Side of the Market

Equipment suppliers
Which projects will order cooling, switchgear, transformers, and racks in the next twelve months, and who is writing the spec.
Engineering and construction firms
New projects, their schedules, and their owners before the RFP circulates.
Developers and operators
Where power is contracted, what competitors are building, and how fast permits are clearing in each county.
Infrastructure investors
Ownership, pipeline, delivery risk, and schedule slippage, project by project, across every target market.
AI infrastructure teams
Liquid-cooled, GPU-ready capacity that is energized today, or will be on a date you can plan around.
Weekly Newsletter
New Data Center Projects Every Week
Stay up to date with the latest research. Subscribe to the free newsletter or upgrade for full access.
Next Steps
Your Market, on the Record
Name the market. We will reply with data where each project is staged, sourced, and dated or scope a 30-day pilot around the question you need answered.